DATA CENTRE CASE STUDY:


          LOUGHBOROUGH UNIVERSITY






                                                             https://commons.wikimedia.org/wiki/File:Lufbra_HazleriggBuilding.jpg



          Established in 1909, Loughborough University          physical IT infrastructure services for the public
          has approximately 19,500 students spread              sector, SMEs and corporate entities. In phase one
          across a 523-acre campus. It is ranked first in       the floor was upgraded and a new EcoStruxure
          the world for sports-related subjects and was         Row Data Centre installed. In phase two the IT
          named Sports University of the Year by The            was migrated back into the new installation
          Times and The Sunday Times.                           with increased floor space created for future IT
                                                                deployments.
          Central to the efficient running of the university
          is its two primary data centres that act as a         Another issue which later transpired concerned
          failover to each other, namely the Haslegrove site    the chilled water systems. The chillers on the
          (constructed in the 1950s) and the more recent        roof suffered catastrophic failure during the hot
          Holywell site, which began operations in 2010.        summer of 2022, compromising the university’s
                                                                commitment to no single point of failure. In
          By this time the Haslegrove data centre had
                                                                order to address this Schneider Electric’s InRow
          evolved to the point where it had around 60 server
                                                                DX (direct expansion) units were installed to
          racks, with different faculties adding new racks
                                                                accompany the new EcoStruxure Row Data
          ad-hoc over the years. This gave rise to a number
                                                                Centre so as to create two separate circuits,
          of challenges as the dynamics of the server load
                                                                extending the ‘no single point of failure’ design
          grew more complex, with hotspots emerging
                                                                concept throughout the entire facility. It also
          when the room’s cooling units became unable to
                                                                used containment to gain more cooling control
          deliver sufficient cool air.
                                                                and cool the IT racks directly. As a result the
          When the university virtualised its server load       environment became better suited for a new
          the resulting reduction in the number of IT racks     generation of compact and powerful servers. This
          meant that the layout of Haslegrove had to be         was done at both Haslegrove and Holywell.
          redesigned, necessitating segregation of the the
                                                                Additionally, the university has installed Schneider
          air supplies in order to optimise cooling efficiency.
                                                                Electric’s EcoStruxure IT platform in order to
          The task was awarded to Schneider Electric’s          proactively anticipate any failures and take action
          Hot Aisle Containment Solution (HACS), formerly       to mitigate them before they become critical.
          known as Infrastruxure and now referred to
                                                                Further improvements in resilience and efficiency
          as EcoStruxure Row Data Centre. This is a pre-
                                                                were also achieved by replacing legacy UPSs
          engineered, modular, scalable and highly
                                                                (Uninterruptable Power Supplies) with Schneider
          configurable system incorporating integrated
                                                                Electric’s Galaxy VS UPS with lithium-ion batteries.
          power, racks, cooling and management software.
                                                                This incorporates Schneider Electric’s patented
          It was also deployed at the Holywell site.
                                                                eConversion operating mode which offers
          Ten years later the containment system                up to 99 per cent energy efficiency without
          approached the end of its useful operational life.    compromising availability, and is noted to have
          In addition, the original 1950s floor at Haslegrove   increased resilience for the university’s research
          had started to become unstable in places and          applications.
          needed replacement.
                                                                [ Reference: ‘Loughborough Uni drives IT and Data
          A two-phase upgrade project followed involving        Centre Efficiency with Schneider Electric’, Data
          Schneider Electric’s Elite partner on365, a           Centre Review, Autumn 2023 ]
          specialist in the provision of energy efficient